Which management strategy involves outlining tasks to track project progress?

Prepare for the Ontario Condominium Management License Test with flashcards and multiple choice questions, each equipped with hints and explanations. Get ready for success!

The correct answer is a Project Plan, as it specifically involves detailing the tasks, timeline, and resources necessary to achieve specific project goals while tracking progress throughout the project lifecycle. A Project Plan creates a structured framework that allows project managers and teams to see what needs to be done, allocate responsibilities, set deadlines, and monitor the completion of each task. This comprehensiveness ensures that any obstacles can be addressed promptly, and the project stays on track toward its objectives.

Operational Management, while crucial for day-to-day operations and efficiencies within an organization, does not focus specifically on tracking the progress of projects but rather on ensuring that routine operations are conducted effectively.

Strategic Initiative typically refers to broader long-term goals and directions of an organization rather than the granular tracking of specific tasks within a project.

Performance Review is more about evaluating the efficiency and outcomes of an individual or team's work rather than on establishing a framework for tracking the ongoing progress of projects. Thus, the Project Plan is uniquely suited to the task of outlining and monitoring the sequence of activities necessary for successful project completion.